Data Centre Development

Data Centre Development

Having received several repeat commissions from Plannet 21 Communications, we were appointed to provide a range of services for their new €20m data centre development in Ballycoolin Business Campus. Housed within an existing warehouse building, some of the major alterations required included additional mezzanine floors, alterations to existing structural elements, installation of a significant amount of external cooling plant and backup generators with a new 5m tall screen wall.

Key Tasks and Challenges:

  • Data Centre development
  • Planning applications
  • Fire Safety applications and inspections
  • Assigned Certifier
  • Civil and Structural alterations to existing building

Client: Plannet 21 Communcations Ltd
Budget: €20,000,000
Architect: N/A